Custom Sprint Durations cannot be used with legacy Sprint Dashboard cards. If you need to use Custom Sprint Durations with Sprint reporting cards, switch to our new Sprint Velocity, Burnup, and Burndown cards.
Sprint card feature availability and limits vary by plan and user role. Learn more
Burndown legacy charts
- The blue line shows the amount of work remaining in your project.
- The yellow line represents the current rate of progress.
- The red line represents the ideal rate of progress based on the remaining time. If your tasks stay at or under the red line, it means you're on track to finish your project on time.
Adding more tasks to your project or sprint will cause an upward trend.
Add a Burndown (legacy) card
- Create a new or open an existing Dashboard.
- In the upper right corner, click + Add card.
- From the left sidebar, select Sprints.
- Click the Burndown (legacy) card.
- Configure your card settings.
- In the upper-right, click Add card.
Burndown legacy card settings
Choose the data and appearance of your Burndown (legacy) card.
The following table describes the available card settings:
Setting Group | Setting | Description |
Source type | Source type | Options include:
|
Data Source |
Select locations | Choose the Spaces, Folders, and Lists to include. |
Include Subtasks | Include subtasks from the selected locations. | |
Include Tasks in Multiple Lists | Include tasks added to the selected locations. | |
Include Subtasks in Multiple Lists | Include subtasks added to the selected locations. | |
Display | Show legend | Show the color and value of each y-axis group by option. |
X-Axis | Measure |
Burndown (legacy) cards always display task data over time. Learn more The only option available for Burndown (legacy) cards is Time. |
Time period |
Include task data from the selected time range. Options include:
When using Sprints as the Source type, the only option is Set dates that align with the selected Sprints. |
|
Group by |
Display x-axis values in the selected time scale. Options include:
|
|
Y-Axis |
Measure |
Options include:
|
Group by | The only option available for Burndown (legacy) cards is Status Type. | |
Show | The only option available for Burndown (legacy) cards is Active. | |
Filters | Show archived |
Include archived tasks. |
Filter | Apply filters to show tasks that currently meet the specified criteria. |