Sprint Burnup cards (Legacy)

A Burnup card is a Sprint card available in our Dashboard feature.

Sprint card feature availability and limits vary by plan and user role. Learn more

Our new Sprint Burnup cards offer improved accuracy and performance! Existing Sprint cards and legacy Burndown cards are still available.

Burnup cards allow you to see data from as early as August 2020.

Custom Sprint Durations cannot be used with legacy Sprint Dashboard cards. If you need to use Custom Sprint Durations with Sprint reporting cards, switch to our new Sprint Velocity, Burnup, and Burndown cards.

Burnup cards

This card lets you create a burnup chart, which is a visual representation of your project’s progress that highlights:

  • Work you’ve completed
  • Total project work

It’s an easy way for Agile project managers to track what’s been completed against their total scope of work.

Screenshot of a Burnup Card.

Y-axis: The grey line represents the total amount of work to do, reflected using Sprint Points on y-axis.

X-axis: The green line represents the total work that has been completed over time (shown on the x-axis).

Once all the work is done, the green line will intersect the grey line, signaling the end of the project.

If you add tasks to your project or Sprint, you will see an increase in the grey line representing total work to be done*.*

Add a Burnup Card

To add a Burnup card:

  1. Create a new or open an existing Dashboard.
  2. In the upper right corner, click + Add card.
  3. From the left sidebar, select Sprints.
  4. Click the Burnup (legacy) card.
  5. Configure your card settings.
  6. In the upper-right, click Add card.

Burnup legacy card settings

Choose the data and appearance of your Burndown (legacy) card.

The following table describes the available card settings:

Setting Group Setting Description
Source type Source type Options include:


• Sprints
• Lists
• Custom Fields: tasks with Label or Dropdown Custom Fields.
Data Source Select locations Choose the Spaces, Folders, Subfolders, and Lists to include.
Data Source Include Subtasks Include subtasks from the selected locations.
Data Source Include Tasks in Multiple Lists Include tasks added to the selected locations.
Data Source Include Subtasks in Multiple Lists Include subtasks added to the selected locations.
Display Show legend Show the color and value of each y-axis group by option.
X-Axis Measure Burnup (legacy) cards always display task data over time. Learn more
The only option available for Burnup (legacy) cards is Time.
X-Axis Time period Include task data from the selected time range. Options include:

• This year
• This month
• This week
• Rolling period
• Range When using Sprints as the Source type, the only option is Set dates that align with the selected Sprints.
X-Axis Group by Display x-axis values in the selected time scale. Options include:

• Days
• Weeks
• Months
Y-Axis Measure Options include:

• Number of tasks
Time Estimate
Average age of tasks
Sprint points
Custom Fields
Y-Axis Group by The only option available for Burnup (legacy) cards is Status Type.
Y-Axis Show The only option available for Burnup (legacy) cards is to include both Done and Closed.
Filters Show archived Include archived tasks.
Filters Filter Apply filters to show tasks that currently meet the specified criteria.