Rescheduling dependencies

Automatically keep your dependent tasks up-to-date when blocking tasks are completed or delayed.

Feature availability and limits vary by plan and user role. Learn more

Rescheduling dependencies

When tasks are connected with a dependency relationship, and the due date of a blocking task is updated, ClickUp automatically adjusts the start and due dates of any tasks waiting on the blocking task.

For example:

Task A is blocking task B. Both tasks have start and due dates set.

Task A's due date is moved one week into the future.

ClickUp automatically updates Task B's start and due dates one week into the future.

Use the Reschedule Dependencies, Duration, Remap Subtask Due Dates, and Only Use Working Days for Scheduling ClickApps to automatically keep your project tasks on track and up-to-date.

Activate the Rescheduling Dependencies ClickApp

To activate the Rescheduling Dependencies ClickApp:
  1. Open the App Center.
  2. From the App Center's left sidebar, click Scheduling & Dates.
  3. Browse or search for the Rescheduling Dependencies ClickApp.
  4. Click the toggle to activate the Rescheduling Dependencies ClickApp.
  5. Click the Enabled in dropdown to choose which Spaces will use rescheduling dependencies.

Reschedule tasks

To reschedule a task with dependencies:

  1. Open a task that is blocking one or more other tasks.

    Both tasks must have a due date.

  2. Change the due date of the blocking task.
  3. The start and due dates of any dependent tasks are updated by the same amount of time.

Reschedule dependencies in List view and tasks

You can also reschedule dependencies from List view or from a task.

Changing the due date of tasks with dependencies to a later date automatically reschedules the start and due dates of all of their dependent tasks across the Workspace by the same amount.

Dependencies are not rescheduled if:

  • The due date is moved to an earlier date.
  • The start date is updated.

Reschedule dependencies in Gantt view

From a Gantt view you can enable an option to reschedule dependencies.

When you enable the Reschedule Dependencies ClickApp, the setting in Gantt views is automatically enabled.

When rescheduling dependencies from Gantt view, only visible tasks and their dependencies are rescheduled.

Manually reschedule tasks from Gantt view

With the Reschedule Dependencies ClickApp activated, you can disable the setting from the Customize menu in Gantt view to manually reschedule your tasks from the Gantt view.

Reschedule tasks in Gantt view

To reschedule tasks from a Gantt view:

  • Drag and drop a task to an earlier or later date.
  • Click and drag the right end of a task to adjust the due date.