Use baselines to create visual snapshots of your task dates in Gantt views.
Baselines capture the start and end dates of the tasks in a List, Folder, or Space, at a point in time.
Add a baseline at any time during your projects to show how tasks have accelerated or been delayed.
Baselines are available on Gantt views on Lists, Folders, and Spaces, so you can capture detailed baselines for each project and high-level baselines for your portfolio and strategic initiatives.
Feature availability and limits vary by plan and user role. Learn more
Permissions to work with baselines
What you can do with baselines depends on your permissions to the List, Folder, or Space:
- Full Edit: Can create, rename, delete baselines.
- Edit: Can show or hide baselines and save view changes.
- Comment or View only: Can show or hide baselines and export.
Create a baseline from Gantt view
To create a baseline, from a Gantt view:
- Click Customize.
- Select Baselines.
- Click Add Baseline.
Show or hide baselines on Gantt view
Show or hide baselines, from a Gantt view:
- In the upper-right corner, click Customize.
- Select Baselines.
- Click the toggle to show or hide each baseline.
- The created date and time are displayed under each baseline's name.
You can also show or hide baselines from the baselines legend.
Baselines legend
When one or more baselines are added to a Gantt view, you'll see a legend in the lower-right corner.
The legend displays the name and color of each baseline.
From the baselines legend, you can:
- Click a baseline from the legend to show or hide it on your Gantt view.
- Click the settings cog icon to add and edit baselines.
- Click the X to hide all baselines and the baselines legend.
Edit a baseline
To edit a baseline, from a Gantt view:
- In the upper-right corner, click Customize.
- Select Baselines.
- Hover over a baseline.
- Click the ellipsis ... icon.
- Edit your baseline. Options include:
- Rename: Update the name of your baseline.
- Color: Set the color of the baseline displayed under your tasks.
Delete a baseline
This is a permanent action. Deleted baselines cannot be restored.
To delete a baseline, from a Gantt view:
- In the upper-right corner, click Customize.
- Select Baselines.
- Hover over a baseline.
- Click the ellipsis ... icon.
- Click Delete baseline.
Export Gantt view with baselines
When baselines are shown on a Gantt view, they are included in the lower-left corner of an export.