Create Dependency Relationships between tasks in List, Board, Calendar, and Gantt views.
What you'll need
- Dependency Relationships are available on all plans.
- Everyone, including guests with edit or full permissions, can create task Dependencies.
- Task dependencies are not available on the ClickUp mobile app.
See and create Dependencies in views
Tasks with Dependencies are displayed with a Dependency icon next to the task name in List, Board, and Calendar views.
There are three ways to open the Dependency Relationships modal from views:
- Click the Dependency icon.
- Right-click a task and select Dependencies.
- Hover over a task, click the ellipsis ... menu on the right, then select Dependencies.
From the Dependency modal, you can add and remove tasks.
Add the Dependencies column to List view
To add the Dependency Relationships as a column in a List view:
-
Open the List view.
-
In the upper-right corner above the task table, click the plus icon.
-
Search or browse for Dependencies.
-
Select an existing Dependency field or select Dependencies to create a new one.
-
The Dependencies column will display any waiting on or blocking tasks.
Add tasks in the Dependencies column
Once you've added the Dependencies column to a List view, you can create Dependencies.
To add waiting on and blocking tasks:
- Click the Dependencies column to the right of a task.
- Click + Add task.
- Select Waiting on or Blocking.
- Search or browse for tasks.
Unlink tasks from the Dependencies column
Once you've added the Dependencies column to a List view, you can unlink Dependencies.
To unlink dependent tasks:
- Click the Dependencies column to the right of a task.
- Hover over an existing related task.
- Click the x on the right.
See Dependencies in Gantt view
You can view Dependencies in Gantt view.
Dependency Relationships are displayed as arrows connecting tasks. The direction of the arrow represents the type of Dependency.
For example, task A is blocking task B. The arrow will start at task A and end at task B.
Create Dependencies in Gantt view
To create a Dependency between two tasks in Gantt view:
- Open a Gantt view.
- Hover over a task to reveal the connector icon.
- Click the connector icon at the start or end of a task.
- Drag the line to the start or end of another task.
- Release the mouse button to create the Dependency.
To remove a Dependency between tasks, double-click the line between tasks.